Concrete quantity guide: cubic metres, allowance, cement, aggregate and water

Short answer: concrete volume = length × width × thickness in metres, summed for all elements and increased by an allowance. A 5 × 4 m slab 12 cm thick is 2.4 m³, and with a 5 % allowance 2.52 m³. Here are the formulas for slabs, footings and columns, the allowance, order rounding, weight and typical ingredients for hand mixing, with examples calculated by the concrete calculator.

1. Volume per element

A slab, pad footing, strip footing, beam and column are calculated as length × width × height. Divide centimetres by 100: 12 cm = 0.12 m. A round column or footing is π × r² × height. The calculator adds up the volumes of all elements; openings are subtracted only for slabs (for example a stair or chimney opening).

Examples: strip footing 10 × 0.4 × 0.5 m = 2 m³; round column Ø 0.4 m, 3 m high: π × 0.2² × 3 = 0.377 m³.

2. Allowance and order rounding

An allowance of 5 % or 10 % is added to the total volume for an uneven excavation bottom, formwork deflection and losses during pouring. The volume with allowance is rounded up to 0.01, 0.1 or 1 m³, depending on how your supplier takes orders. A 2.4 m³ slab with 5 % gives 2.52 m³, and the order rounded to 0.1 m³ is 2.6 m³.

3. Concrete weight

The calculator estimates weight as volume with allowance × 2400 kg/m³. This helps estimate transport and loads: 2.1 m³ of concrete weighs about 5040 kg. Do not confuse volume and weight – 1 m³ of concrete is not 1 tonne but about 2.4 tonnes.

4. Ingredients for hand mixing (C25/30)

For class C25/30 the calculator uses, per m³, 350 kg of cement, 0.5 m³ of sand, 0.8 m³ of gravel and 180 L of water; cement is rounded up to 25 kg bags. The table shows values without the allowance.

Volume (m³)Cement (kg)25 kg bagsSand (m³)Gravel (m³)Water (L)
1350140.50.8180
27002811.6360
51750702.54900
103500140581800

5. Example: strip footing

Footing 10 × 0.4 × 0.5 m = 2 m³; a 5 % allowance gives 2.1 m³. C25/30: cement 350 × 2.1 = 735 kg, so 30 bags of 25 kg; aggregate (0.5 + 0.8) × 2.1 = 2.73 m³; water 180 × 2.1 = 378 L. For a 5 × 4 × 0.12 m slab with 5 %: 2.52 m³, cement 882 kg (36 bags), aggregate 3.28 m³ and about 454 L of water.

6. Common mistakes and limits

  • Leaving out the allowance, so the last pour runs short.
  • Entering thickness in centimetres as metres – 12 instead of 0.12 gives a volume a hundred times too large.
  • Typical hand-mix recipes are not proof of quality; for load-bearing parts the concrete class and mix are set by the structural design and the ready-mix plant.
  • The calculator does not calculate reinforcement (use the rebar calculator), compaction, pump placement or a truck mixer's minimum order.

Frequently asked questions

How do I calculate cubic metres of concrete?

Multiply length × width × thickness in metres and add up all elements. A 5 × 4 m slab 12 cm thick is 2.4 m³; with a 5 % allowance 2.52 m³, and rounded to 0.1 m³ you order 2.6 m³.

How much cement per m³ of C25/30 concrete?

The calculator uses 350 kg per m³, which is 14 bags of 25 kg.

How much does 1 m³ of concrete weigh?

About 2400 kg; the calculator uses this value for weight.

How much sand, gravel and water per m³ of C25/30?

The calculator uses 350 kg of cement, 0.5 m³ of sand, 0.8 m³ of gravel and 180 L of water per m³. These are indicative mixes; structural concrete follows the design.

How do I order ready-mix concrete?

Give the volume with reserve, the strength class, exposure class, consistency and maximum aggregate size. The calculator rounds the order up to 0.1 m³.

When can the formwork be removed?

It depends on temperature and the element: wall and footing sides often after 1–3 days, slab soffits only when the concrete is strong enough, often after 2–4 weeks with props, as the structural engineer specifies.